Taos Town Council
Tuesday, June 23, 2026 · Town Council Regular Meeting
Summary
The Town Council held a regular meeting to consider airport terminal change orders, a restroom building for Filemon Sanchez Sports Complex, airport engineering services and a copier lease.
Staff brought a $446,455.80 quote from CXT Inc. for a pre-manufactured, multi-user restroom building at Filemon Sanchez Sports Complex. Three change orders from Mick Rich Contractors for the Terminal Project at Taos Regional Airport were listed: $72,915.10 for low-voltage rough-in, $303,545.60 for mechanical and electrical revisions due to changed drawing sets, and $102,240.54 for quantity overruns. Staff also brought an award of RFP 25-26-12 to LJA Engineering, Inc. for airport engineering services and a 48-month Xerox copier lease at $30,613.80 a year, $122,455.20 over the term.
The Mayor was to appoint a member and alternate to the Taos County Economic Development Corporation Board. A closed executive session was also listed. The Town has not posted minutes, so the results of the votes are not yet known.
Decisions and items
- Outcome not in the posted record yet Quote PM20260615 from CXT Inc. to buy and install a pre-manufactured, multi-user restroom building at Filemon Sanchez Sports Complex, $446,455.80 including gross receipts tax, using Sourcewell Contract 052725-CXT.
- Outcome not in the posted record yet Change Order Number 5 from Mick Rich Contractors for low-voltage rough-in per design on the Taos Regional Airport Terminal Project, $72,915.10 including gross receipts tax.
- Outcome not in the posted record yet Change Order Number 8 from Mick Rich Contractors for revisions to mechanical and electrical equipment due to changed drawing sets on the Terminal Project, $303,545.60 including gross receipts tax.
- Outcome not in the posted record yet Change Order Number 12 from Mick Rich Contractors to cover the overrun of quantities on the Terminal Project, $102,240.54 including gross receipts tax.
- Outcome not in the posted record yet Award of RFP 25-26-12 for airport engineering services to LJA Engineering, Inc., with authorization for the Mayor to sign the master service agreement.
- Outcome not in the posted record yet A 48-month lease for Xerox multifunction copiers for Town-wide use, $30,613.80 a year and $122,455.20 over the four-year term including gross receipts tax, using NASPO Contract 072848600.
- Outcome not in the posted record yet Appointment of a member and alternate to the Taos County Economic Development Corporation Board.
The official record
Written from the official agenda, video.
How these are written: each summary comes from the official agenda, minutes and meeting video, and is checked before it is posted. They say what was on the table and what was decided, not who was right. Where the minutes are not posted yet, the outcome says so. Always check the official record; found a mistake? Tell us.